Binondo-Intramuros Bridge is now 77 percent complete, DPWH says

Updated Dec 20, 2021 | Same topic: Latest Traffic Updates

It’s inching closer to a 2022 opening.   

The Department of Public Works and Highways (DPWH) reports that the Intramuros-Binondo Bridge is currently at 77 percent completion, putting it on track to open by early next year. 

Binondo-Intramuros Bridge

The new bridge is being prepared for a 2022 opening to the public

According to DPWH Secretary Mark Villar, workers on the project have nearly finished installing the fabricated precast concrete slab panels on the assembled steel beams, following the completion of the sling cable tensioning components. These will comprise the main bridge carriageway. Meanwhile, there are 114 out of 135 piles completed which will be used for abutments, piers, and ramps, with the remaining 21 mostly located at the Estero De Binondo area. 

One challenging aspect of the project is the presence of overhead lines for electricity and other utilities at the bridge’s north approach. DPWH Undersecretary for Unified Project Management Office (UPMO) Operations Emil Sadain conducted a field assessment with Project Manager Melchor Cabiling, to observe how the cables can potentially affect the launch of the steel box girders needed for the down-ramp portion. 

DPWH inspection

DPWH officials conducted a field assessment of the project 

The high-tension wires and distribution poles propping them up pose a serious safety concern for the construction of the ramps at both the Binondo and Intramuros points of the bridge. Sadain said that the DPWH UPMO Roads Management Cluster 1 is following up on its request to the Manila Electric Company (Meralco) and telecom companies to relocate the cables and posts.

Funded through a China Aid grant at an estimated project cost of Php 3.39 billion, the Binondo-Intramuros Bridge spans 680 meters while buoyed by basket-handle tied steel arches. This is accompanied by a viaduct structure over Estero De Binondo.      

Binondo-Intramuros Bridge works

Workers are about to complete the installation of concrete slabs  

Construction of the bridge has been slowed down due to pandemic lockdowns, but the DPWH said that it has been taking proactive and preventive measures for workers, in cooperation with contractor China Road and Bridge Corporation. The DPWH plans to open the bridge to the public by the first quarter of 2022. 

We’ll bridge the gap in your knowledge of transport infrastructure at Philkotse.com.  

Joseph Paolo Estabillo

Joseph Paolo Estabillo

Author

Joseph holds a degree in Journalism from the University of the Philippines Diliman and has been writing professionally since 1999. He has written episodes for CNN Philippines' motoring show Drive, and has worked on corporate projects for MG Philippines and Pilipinas Shell. Aside from being Philkotse.com’s Content Lead, he also writes content for numerous car dealerships in the U.S., spanning multiple brands such as Alfa Romeo, Chrysler, Dodge, Jeep, and Maserati, among others.

Facebook: https://www.facebook.com/kapatilya

View more